Project Timeline
Keep track of our progress as we move through the planning application process for the Golden Mile West redevelopment proposal. You can also learn more about upcoming engagement opportunities and project milestones.
Official Plan Amendment (OPA)
Key project and engagement milestones related to the OPA Application
-
2018
-
Meeting with City Staff
July, 2018
-
2019
-
Drop-in Tenant Open House
September, 2019
-
Meeting with City Councillor
November, 2019
-
Official Plan Amendment (OPA) Application Submission
November, 2019
-
Tenant Letter
December, 2019
-
2021
-
Tenant Letter
April, 2021
-
2022
Zoning By-Law Amendment (ZBA)
Key project and engagement milestones related to the ZBA Application
-
2023
-
Zoning By-Law Amendment Application Submission
July, 2023
-
2024
-
Letter to Tenants
January, 2024
-
Project Website, Email & Phone Number Launch
February, 2024
-
Tenant 1-on-1 Discussions
February, 2024
-
Letter to Tenants
March, 2024
-
Community Consultation Meeting
March, 2024
-
Application Resubmission
September, 2024
Upcoming Events
Upcoming milestones and engagement opportunities
-
2024
-
Ongoing Updates/Communications to Tenants regarding Future Milestones
Fall, 2024
-
2025
-
City-Led Tenant Consultation Meeting
-
Decision on ZBA Application at Scarborough Community Council & Toronto City Council
-
Site Plan Application Process Continues